Outdoor Furniture
Supply and Installation of Bike Rack
a. Preparation
- Obtain approval for materials and shop drawings. Ensure the area is clear and free of debris before starting.
- Verify and mark the location as per the approved drawing.
b. Installation
- Obtain approval for materials and shop drawings. Ensure the area is clear and free of debris before starting.
- Verify and mark the location as per the approved drawing.
c. Final Steps
- Allow concrete to cure for at least 7 days before applying any load.
- Cover and protect the bike rack until final inspection and approval.
Supply and Installation of Precast Concrete Benches
a. Preparation
- All materials must be approved before installation. Clear and level the area, ensuring access is available
b. Bench Placement
- Place the bench in its designated location and orientation, ensuring the area is ready and paving work is completed.
- Set the bench to be perfectly level and aligned as per drawings
c. Protection and Inspection
- Cover and protect the bench after placement. Issue a Work Inspection Request (WIR) for inspection.
- Final approval is required before moving to subsequent finishes.
Supply and Installation of Metal/Wood Benches
a. Site Preparation
- Clean the installation area, and confirm layout points with a surveyor using total station or similar tools.
- Mark and excavate holes for foundations if in-ground installation is needed.
b. Bench Installation
- Position the bench according to layout, ensuring the area is level.
- Use wedge anchor installation or in-ground post installation methods, securing the bench with concrete and anchor bolts.
c. Final Steps
- Protect the bench and restrict access until the concrete has fully set.
- Submit WIR for final inspection and ensure approval before public use.
Supply and Installation of Precast Concrete Picnic Table and Bench
a. Preparation
- Clear and prepare the area, ensuring access and verifying layout with survey instruments.
- Mark the foundation area and excavate to required dimensions. Compact the subgrade and cover with a polythene sheet.
b. Foundation and Placement
- Place a concrete block at the center for table support, then secure supports in position.
- Pour concrete and allow it to cure for at least 7 days before placing surrounding materials.
c. Installation and Inspection
- Install the picnic table and bench over the concrete base and protect it.
- Raise WIR for inspection after installation and before final acceptance.
Supply and Installation of Precast Ping-Pong Outdoor Table
a. Preparation
- Install the picnic table and bench over the concrete base and protect it.
- Raise WIR for inspection after installation and before final acceptance.
b. Installation
- Place the ping-pong table on a stable, level surface, ensuring alignment and orientation per design.
- If anchoring is needed, use in-ground posts with concrete foundations.
c. Protection and Final Inspection
- Cover and protect the table from damage. Submit WIR for final inspection.
- Obtain consultant approval before opening for use.
Supply and Installation of Litter Bin
a. Preparation
- Approve all materials and confirm installation locations with clear site access
b. Placement and Leveling
- Place the litter bin on the prepared surface, aligning it to the approved location.
- Ensure the bin is level and properly positioned.
. Final Steps
- Protect the bin until inspection, submitting WIR for quality verification.
- Obtain final approval before allowing use.
Supply and Installation of Powder Coated Steel and Aluminium Plates 3-Container Bins, Including Ground Fixing
a. Preparation
- Ensure that materials and shop drawings have been approved by the client/engineers.
- Clear the installation area of debris and confirm access routes.
b. Setting Out and Marking
- In-Ground Post Installation: If the bins require in-ground mounting, excavate holes for each bin post, insert the posts, and secure with concrete.
- Wedge Anchor Installation: For surface mounting, drill holes to the specified depth, insert wedge anchors, and secure the bins by tightening anchor bolts.
c. Final Steps
- Ensure that the bins are level and properly oriented. Cover and protect the bins to prevent damage.
- Submit a Work Inspection Request (WIR) for approval by quality control prior to final acceptance.
Supply and Installation of Rock Clusters
a. Preparation and Site Clearing
- Obtain approval for the rock materials and the layout from the consultant.
- Clear the site of any obstructions and prepare the ground by compacting the subgrade to provide a stable base.
b. Setting Out and Placement
- Mark the layout for the rock clusters, following the approved drawings for size and placement.
- Use geotextile fabric over the compacted surface to prevent soil mixing with the rock cluster base.
c. Rock Placement
- Carefully position each rock in the marked locations, ensuring a natural arrangement with minimal gaps.
- If using heavy machinery, utilize slings to avoid surface damage on the rocks.
d. Finishing and Inspection
- Compact surrounding materials to secure the rocks in place and create a seamless integration with the landscape.
- Submit WIR for final inspection and client approval.
Supply and Installation of Outdoor Lounge Seat
a. Preparation and Layout Confirmation
- Ensure all lounge seat materials are approved. Clear the area and verify the layout using survey equipment for accurate placementWedge Anchor Installation.
b. Setting Out and Foundation Preparation
- Mark the location as per the approved shop drawings.
- For in-ground installation, excavate the required foundation hole, ensuring proper compaction of the subgrade.
c. Lounge Seat Installation
- Insert the lounge seat posts into the prepared holes, suspending the seat to be level and aligned.
- Pour concrete around the posts to secure the seat, allowing it to cure for at least 7 days.
d. Protection and Inspection
- Cover the lounge seat to protect it from potential damage.
- Submit WIR for quality control inspection before releasing the area for use.
Supply and Installation of Outdoor Lounge Seat with Surface Mounting
a. Preparation
- Clear the installation area and ensure materials and drawings are approved.
- Verify the location with survey equipment, marking it accurately as per layout requirements.
b. Foundation and Anchoring
- For surface mounting, position the lounge seat on the marked location.
- Use wedge anchor installation by drilling holes into the concrete, inserting anchors, and tightening nuts to secure the seat.
c. Final Adjustment and Protection
- Ensure that the lounge seat is level and stable, making any adjustments as needed.
- Protect the lounge seat until the concrete and fixings are fully set, and submit WIR for quality control inspection.