Outdoor Furniture

Supply and Installation of Bike Rack

a. Preparation

  • Obtain approval for materials and shop drawings. Ensure the area is clear and free of debris before starting.
  • Verify and mark the location as per the approved drawing.

b. Installation

  • Obtain approval for materials and shop drawings. Ensure the area is clear and free of debris before starting.
  • Verify and mark the location as per the approved drawing.

c. Final Steps

  • Allow concrete to cure for at least 7 days before applying any load.
  • Cover and protect the bike rack until final inspection and approval.

Supply and Installation of Precast Concrete Benches

a. Preparation

  • All materials must be approved before installation. Clear and level the area, ensuring access is available

b. Bench Placement

  • Place the bench in its designated location and orientation, ensuring the area is ready and paving work is completed.
  • Set the bench to be perfectly level and aligned as per drawings

c. Protection and Inspection

  • Cover and protect the bench after placement. Issue a Work Inspection Request (WIR) for inspection.
  • Final approval is required before moving to subsequent finishes.

Supply and Installation of Metal/Wood Benches

a. Site Preparation

  • Clean the installation area, and confirm layout points with a surveyor using total station or similar tools.
  • Mark and excavate holes for foundations if in-ground installation is needed.

b. Bench Installation

  • Position the bench according to layout, ensuring the area is level.
  • Use wedge anchor installation or in-ground post installation methods, securing the bench with concrete and anchor bolts.

c. Final Steps

  • Protect the bench and restrict access until the concrete has fully set.
  • Submit WIR for final inspection and ensure approval before public use.

Supply and Installation of Precast Concrete Picnic Table and Bench

a. Preparation

  • Clear and prepare the area, ensuring access and verifying layout with survey instruments.
  • Mark the foundation area and excavate to required dimensions. Compact the subgrade and cover with a polythene sheet.

b. Foundation and Placement

  • Place a concrete block at the center for table support, then secure supports in position.
  • Pour concrete and allow it to cure for at least 7 days before placing surrounding materials.

c. Installation and Inspection

  • Install the picnic table and bench over the concrete base and protect it.
  • Raise WIR for inspection after installation and before final acceptance.

Supply and Installation of Precast Ping-Pong Outdoor Table

a. Preparation

  • Install the picnic table and bench over the concrete base and protect it.
  • Raise WIR for inspection after installation and before final acceptance.

b. Installation

  • Place the ping-pong table on a stable, level surface, ensuring alignment and orientation per design.
  • If anchoring is needed, use in-ground posts with concrete foundations.

c. Protection and Final Inspection

  • Cover and protect the table from damage. Submit WIR for final inspection.
  • Obtain consultant approval before opening for use.

Supply and Installation of Litter Bin

a. Preparation

  • Approve all materials and confirm installation locations with clear site access

b. Placement and Leveling

  • Place the litter bin on the prepared surface, aligning it to the approved location.
  • Ensure the bin is level and properly positioned.

. Final Steps

  • Protect the bin until inspection, submitting WIR for quality verification.
  • Obtain final approval before allowing use.

Supply and Installation of Powder Coated Steel and Aluminium Plates 3-Container Bins, Including Ground Fixing

a. Preparation

  • Ensure that materials and shop drawings have been approved by the client/engineers.
  • Clear the installation area of debris and confirm access routes.

b. Setting Out and Marking

  • In-Ground Post Installation: If the bins require in-ground mounting, excavate holes for each bin post, insert the posts, and secure with concrete.
  • Wedge Anchor Installation: For surface mounting, drill holes to the specified depth, insert wedge anchors, and secure the bins by tightening anchor bolts.

c. Final Steps

  • Ensure that the bins are level and properly oriented. Cover and protect the bins to prevent damage.
  • Submit a Work Inspection Request (WIR) for approval by quality control prior to final acceptance.

Supply and Installation of Rock Clusters

a. Preparation and Site Clearing

  • Obtain approval for the rock materials and the layout from the consultant.
  • Clear the site of any obstructions and prepare the ground by compacting the subgrade to provide a stable base.

b. Setting Out and Placement

  • Mark the layout for the rock clusters, following the approved drawings for size and placement.
  • Use geotextile fabric over the compacted surface to prevent soil mixing with the rock cluster base.

c. Rock Placement

  • Carefully position each rock in the marked locations, ensuring a natural arrangement with minimal gaps.
  • If using heavy machinery, utilize slings to avoid surface damage on the rocks.

d. Finishing and Inspection

  • Compact surrounding materials to secure the rocks in place and create a seamless integration with the landscape.
  • Submit WIR for final inspection and client approval.

Supply and Installation of Outdoor Lounge Seat

a. Preparation and Layout Confirmation

  • Ensure all lounge seat materials are approved. Clear the area and verify the layout using survey equipment for accurate placementWedge Anchor Installation.

b. Setting Out and Foundation Preparation

  • Mark the location as per the approved shop drawings.
  • For in-ground installation, excavate the required foundation hole, ensuring proper compaction of the subgrade.

c. Lounge Seat Installation

  • Insert the lounge seat posts into the prepared holes, suspending the seat to be level and aligned.
  • Pour concrete around the posts to secure the seat, allowing it to cure for at least 7 days.

d. Protection and Inspection

  • Cover the lounge seat to protect it from potential damage.
  • Submit WIR for quality control inspection before releasing the area for use.

Supply and Installation of Outdoor Lounge Seat with Surface Mounting

a. Preparation

  • Clear the installation area and ensure materials and drawings are approved.
  • Verify the location with survey equipment, marking it accurately as per layout requirements.

b. Foundation and Anchoring

  • For surface mounting, position the lounge seat on the marked location.
  • Use wedge anchor installation by drilling holes into the concrete, inserting anchors, and tightening nuts to secure the seat.

c. Final Adjustment and Protection

  • Ensure that the lounge seat is level and stable, making any adjustments as needed.
  • Protect the lounge seat until the concrete and fixings are fully set, and submit WIR for quality control inspection.